top of page

Half Round Clip Fit Aluminium Gutter Installation


Aluminium beaded half round guttering

General Site Working


BS 8000 Workmanship on building sites, Parts 13 through to 16 with respect to above ground drainage and sanitaryware appliances are relevant in general terms.


Handling and Storage


Gutters, downpipes and fittings, particularly with polyester powder coat finish should be handled with care and preferably stored under cover on racks to prevent scratching. Whilst not known to pose any health hazard, it is recommended that protective gloves be worn when handling mill finish aluminium. All lengths are supplied in a protective polythene wrapping with components similarly wrapped and stored in cardboard boxes. If painted product is to be stored outside, cover with tarpaulin to protect against rainfall and direct sunlight as if water gets trapped inside the protective covering and is exposed to warm sunlight then it may leave permanent watermarks on the paint finish. Mill finish items should be stored under cover to avoid uneven oxidisation prior to being fitted.


Cutting and Drilling


Gutter sections may be cut and drilled on site using standard metalworking tools, however the use of angle grinders is not recommended. Where gutters or fittings are powder coated, then cut edges should be de-burred and then repainted with touch-up paint.


Gutter Position


Gutters may be laid level or to a fall of 1:600. Care must be taken to ensure the gutters are not laid too low so rainfall overshoots the gutter, or too high so that damage could be caused by sliding snow. Although at the discretion of the installer and dependant upon local climatic conditions and roof slope/finish, setting out with the front edge of the fascia bracket in line with the pitch of the roof (use straight edge) is a recommended method.


Jointing


Any use of sealant must not be carried out in wet weather or in temperatures below 5°C or above 50°C. All Joint surfaces must be perfectly clean and dry. Only a low viscosity, low modulus sealant must be used to prevent early failure. Ensure that the gutter joint sockets/spigots are correctly aligned with each other to ensure free thermal movement (3-4mm) within the gutter joint.


Fixing


It is important that all fixings are suitable for both the substrate and the load. They must therefore be of the appropriate size and of a compatible material to ensure no electrolytic corrosion occurs. We recommend that stainless steel (preferably austenitic) screws must be used to fix gutters, whether direct, fascia or rafter bracket fixed.


Gutter Fixing


We advise that you ensure the fixing background (e.g fascia board) is securely fixed, level and able to support the weight of the gutter at full capacity and that the roof overhang is correct – see gutter position. Buildings without fascias may need a different type of bracketry. We offer a range of brackets to suit most applications. We offer side and top fix rafter arms as well as rise and fall brackets. The latter do not meet current BS/EN load requirements so advice should be sought on the parameter of their use.


 

Aluminium Fascia Bracket Installation

Start by deciding whether to fit the gutter level or with a fall to 1:600. Fit a bracket at each end of a run. Position brackets correctly for an angle or stopend.



 

Aluminium Fascia Bracket Installation Position

Image 2 shows the bracket positioning for the angle and bracket to take the gutter length.





 

Aluminium fascia bracket maximum centres

We recommend fixing brackets every 750mm and using an additional bracket for each outlet or angle. Ideally using a string line or laser level between the two brackets, set out intermediate brackets at maximum centres of 750mm.


 

Aluminium outlet position

With the use of a plumb or laser line, position outlets over gullies and support with at least one bracket. Also include a bracket per angle (internal or external).



 

Installation of aluminium gutter into aluminium fascia bracket

When fitting outlets and angles tuck the rear face of the gutter underneath the roof finish. Locate the gutter into the fascia bracket and then clip the front edge down into position. After fitting outlets and angles, proceed with fitting the gutter lengths using the same method.

 


Ensure that all fixing surfaces are clean and dry. Placing the union into the groove in the rear face of the gutter and clip down into place on the front edge.



 

Adding sealant to the aluminium union clips

Trim 4-5 mm off top of nozzle so it fits into the large holes in the base of the union, inject low viscosity, low modulus sealant into one of the large holes in the bottom of the union until the sealant appears at both of the smaller holes at the rim of the union. Repeat the action on the other large hole.

 

Cross section of aluminium gutter, union clip, and sealant assembly

Ensure you apply the sealant gently to ensure the void is fully filled. Clean off any excess sealant and then use the same process for every joint until the work is completed.

Aluminium union clip and stopend sealant instructions

Any cut lengths should be de-burred and touched up with touch-up paint prior to installation. For more information or further assistance, please contact us.


bottom of page